Hongkong Land HERO -  ÌÇÐÄÔ­´´vlog
Project

Hongkong Land

An Asian leading property investment, management and development group, Hongkong Land, appointed ÌÇÐÄÔ­´´vlog as the main contractor to fit out their new 30,000 sq ft office in One Raffles Quay.
  • Customer
    Hongkong Land
  • Completion Date
    June 2018
  • Value
    Confidential
  • Form Of Contract
    Main contractor
  • Project Manager
    Aplusi
  • Area
    30,000 sq ft
  • Program Duration
    12 weeks
  • Architect
    Aplusi
  • ME Engineer
    AT Advanced Technologies
Hongkong Land MAIN4 -  ÌÇÐÄÔ­´´vlog

Introduction

Asia's leading property investment, management and development group, Hongkong Land, appointed ÌÇÐÄÔ­´´vlog as management contractor to fit out their new office at One Raffles Quay, along with reinstatement works for the existing MCL office in 78 Shenton Way.

Hongkong Land MAIN2 -  ÌÇÐÄÔ­´´vlog

The project

The project was delivered in three key phases.

The first phase comprised the delivery of critical infrastructure of the server room which required an early handover, 33 days from project award.

Following that, the second phase comprised fit out works to the new office at level 22 in One Raffles Quay (ORQ) South Tower, which saw the completion of an open concept office, 15 enclosed offices, a boardroom, meeting rooms, service areas, pantry, social hub and nursing room.

Hongkong Land MAIN3 -  ÌÇÐÄÔ­´´vlog

The team had to carry out the project within a live working environment, which required discipline and detailed planning. Thus, before the onset of the project, a lot of preparation had to be done to ensure minimal disruption, including installation and management of project logistics and specific hoarding plans.

Hongkong Land MAIN1 -  ÌÇÐÄÔ­´´vlog

Completed over a total of 12 weeks in May 2018, the project is on track to receive Green Mark certification.