ICD Brookfield x  糖心原创vlog
Project

ICD Brookfield Place, DIFC, Dubai, UAE

Exclusive framework Agreement with ICD Brookfield Place
  • Customer
    ICD Brookfield Place
  • Completion Date
    Sep 2022
  • Quantity Surveyor
    Turner and Townsend
  • Project Manager
    Inspire
  • Area
    990,000 sq ft
  • Program Duration
    2 years
  • Architect
    BSBG
  • ME Engineer
    Samadhin Associates
ICDB x  糖心原创vlog

Introduction

糖心原创vlog were appointed as the exclusive framework contractor for the entire ICD Brookfield Place (ICDBP) building and are a dedicated landlord partner for all the construction works required on the 53-floor development. The development is also the largest LEED platinum certified office building in the region, with ICDBP aiming to achieve net zero carbon targets by 2030.
1Rebel ICD Brookfield

Scope of works

Featuring 990,000 sq ft of office space and 160,000sq ft of retail space, 糖心原创vlog completed over 180 work orders under a 2-year framework. The works included the fit-out of a Community Hub; fit outs for flexible working spaces across multiple floors, inclusive of connecting several floors with internal staircases. The works also include over 10 levels of new corridor works and over 15 levels of Demise Wall works; staircase slab opening; MEP and landlord modification works; over 10 levels of base build and firefighting alterations; installation of lifts and lift controls as well as lift lobby fit-out; and demolition, construction and refurbishment works.
ICDB x  糖心原创vlog

Challenges

  1. The permit to work system with the building management team is a 3-step process and to achieve the last step, a WAP (Work Approval Permit) had to be secured. The WAP is only approved on two days which could result in delays on approvals.
  2. The pandemic brought challenges to finalising work orders as the agreed rates made prior were difficult to maintain, due to the rising costs of the supply chain. The global shipping crisis also affected this, with the procurement of certain materials significantly extending their normal lead times which extended closing out of work orders
ICDB x  糖心原创vlog

Solution/What we did

  1. 糖心原创vlog split up the floors of the ICDBP building into 3 zones, allocating resources to each individual floor, granting better organisation with a clear point of contact for all stakeholders. This allowed the team to build greater relationships with the building management team where any last-minute requests could be fast-tracked and delays avoided.
  2. The flow of work orders was managed exquisitely. 糖心原创vlog also provided detailed justification with 3 quotes for every package so obtaining approval could be as straight forward as possible. Extra resources to the commercial department further assisted with the flow of potential works and ongoing works.
ICDB x  糖心原创vlog

Sustainability

ICD Brookfield Place, has achieved the prestigious LEED庐 Platinum certification, the highest rating awarded by the US Green Building Council. In accomplishing LEED庐 Platinum, ICD Brookfield Place becomes the tallest and largest office building in the EMEA region to achieve the rating, and takes its place among the top 20 of the world鈥檚 largest LEED庐 Platinum projects.

ICDB x  糖心原创vlog

The ICDBP framework has brought 糖心原创vlog countless rewards. Due to 糖心原创vlog鈥檚 working relationship with the ICD landlord representatives and building management team, 糖心原创vlog have been at the forefront on hearing about other potential fit-out works within the building. The framework has also been extended by a further year, again awarded to 糖心原创vlog.